Options for Microgrids, Micro Datacentres and RCM Revenue Streams
This briefing explores options for microgrids and potential revenue streams from the WA RCM scheme.
Summary
1. Datacentres
Large datacentres are ruled out: controller software comes bundled with the power hardware, so there is no way in for a separate controller. Micro data centres are an option.
2. RCM revenue streams
A 1 MW / 6 MWh battery can earn capacity payments from the WA Reserve Capacity Mechanism, with participation through an aggregator.
3. Microgrids
A battery, solar and EV chargers behind one grid connection can earn from several sources: avoided grid upgrades, peak shaving, tenant energy sales and capacity payments.
4. Voltron controller
The proprietary control platform developed in-house drives system reliability and maximises project yield. The software gives Voltron complete architectural control, allowing us to tailor dispatch logic, peak-shaving thresholds, and automation protocols directly to each client’s specific operational requirements.
Are datacentre builds an option?
Large datacentre microgrids are mission-critical power systems. It is unlikely that Voltron can compete effectively in this market.
The controller comes with the hardware
The leading switchgear and power makers (Schneider Electric, ABB, Siemens, Eaton) sell their own microgrid management systems with their equipment. Customers and builders expect to buy them together.
Contracts are bundled
Datacentres are delivered through turnkey builders and engineer-procure-construct contracts. The control system is part of the package, so a standalone software supplier has no point of entry.
The technical bar is very high
Datacentre systems must respond in fractions of a second and use proven, certified equipment. Medium-voltage switchgear alone can have lead times of two to three years.
No track record yet
Neither Voltron nor Chargestar has datacentre or grid-scale installations to point to. Buyers in this market rely on references.
Conclusion: the datacentre route would mean competing against the hardware makers on their own ground. We recommend putting the effort into commercial and industrial microgrids, where the controller can be sold as an independent product.
Micro data centres are an option
We are saying no to large datacentres but yes to micro data centres.
- Why it fits: a highly efficient micro data centre, such as those made by Zella DC, uses advanced cooling to reach a Power Usage Effectiveness (PUE) as low as 1.2. Integrated into a commercial battery-based microgrid, it dramatically reduces lifetime operating costs.
- The challenge: these compact units are optimised to minimise energy use, but they still represent a continuous 24/7 baseline IT and cooling load. Left unmanaged, this constant draw can compound the site’s existing peak usage and trigger major Western Power demand ratchet penalties.
- Daytime: placed behind the meter, the unit is powered directly by the site’s own excess rooftop solar generation.
- Evening: as the sun sets and the wider facility enters its evening peak, the microgrid controller automatically discharges the 6 MWh battery to buffer the continuous server load.
- The result: this peak-shaving strategy shields the data workload from volatile wholesale energy spikes and effectively eliminates the associated network demand fees. The outcome is a hyper-efficient edge-computing asset powered largely by localised, free energy.
What is the Reserve Capacity Mechanism and how does it work?
Western Australia’s South West grid is a stand-alone system, so it must always hold enough generating and storage capacity to meet the highest demand, with a safety margin. The Reserve Capacity Mechanism (RCM) pays owners of capacity for being available when needed, whether or not they are used.
- Capacity is certified. A facility is assigned capacity credits for the power it can reliably deliver. The operator is paid on the rated output of the battery over one hour, and the battery must have the capacity to discharge for six hours. A 6 MWh battery discharging at 1 MW over six hours is awarded one capacity credit, which for batteries coming on line in 2027 is worth A$360,700 per year.
- A price is set. The Economic Regulation Authority sets the Reserve Capacity Price, in dollars per MW per year, for each capacity year. It now uses a battery as the reference technology.
- The owner is paid for availability. Each year the facility is paid the price multiplied by its capacity credits, in return for being ready.
- It must be ready when called. The obligation falls on the evening peak. Operators are told the intervals in advance, then receive the dispatch instruction about five minutes before power is needed. The battery must be charged and responding automatically. Missing the obligation attracts financial penalties.
What the payments look like
| Capacity year | Reserve Capacity Price (per MW per year) | Payment for 1 MW |
|---|---|---|
| 2025-26 | A$251,420 | A$251,420 |
| 2026-27 | A$216,092 | A$216,092 |
| 2027-28 | A$360,700 | A$360,700 |
A 6 MWh battery discharging at 1 MW earns one credit, as credits are awarded on a one credit per MW of capacity basis. The price changes with each cycle, so revenue cannot be assumed to stay at the 2027-28 level. Payments are before the aggregator’s share, tax and operating costs.
Can a battery operator in a microgrid take advantage of the RCM while still using the battery for other purposes?
To take advantage of the Reserve Capacity Mechanism (RCM) while dual-purposing the battery for local microgrid needs, an operator must divide the battery’s daily schedule into two operational states. This is achieved by using an intelligent Energy Management System (EMS) to manage the strict compliance boundaries set by the Wholesale Electricity Market (WEM).
The strategy relies on separating the legally binding RCM obligations from free commercial use.
1. Navigating the PESROI window (grid priority)
Under WEM rules, a battery receiving capacity payments does not belong to AEMO 24/7. It is only strictly obligated to the grid during the Peak Electric Storage Resource Obligation Intervals (PESROI), the critical evening peak window defined by AEMO.
- The RCOQ mandate: during the PESROI, the battery has a Reserve Capacity Obligation Quantity (RCOQ). It must hold a sufficient state of charge (SOC) to discharge its contracted megawatt capacity into the broader South West Interconnected System (SWIS) if AEMO issues a 5-minute dispatch instruction.
- Penalty avoidance: if the battery cannot meet this dispatch instruction because it was depleted by local microgrid loads, AEMO will levy severe financial penalties known as Capacity Refunds, which can quickly wipe out the site’s capacity revenue. During this window, grid compliance overrides all local site optimisation.
2. Freedom outside the window (microgrid priority)
Outside of the evening PESROI window, the RCOQ drops to zero. The battery is legally freed from its AEMO capacity obligations and can be cycled for local financial benefit:
- Morning and midday solar soaking: the battery absorbs excess generation from the microgrid’s commercial rooftop solar array that would otherwise be wasted or exported for minimal return.
- Daytime peak shaving: if the site’s commercial operations or EV chargers suddenly spike demand at 1:00 PM, the battery discharges locally to shave the peak, shielding the site from Western Power’s 12-month demand ratchet penalties.
- Wholesale arbitrage: the site’s aggregator can bid the battery’s spare capacity into the 5-minute energy or frequency (FCESS) markets to capture daytime price spikes, provided there is enough time to recharge before the evening peak.
3. The role of the microgrid controller (dynamic SOC management)
To run this dual-use model safely without human intervention, the site must install an advanced microgrid controller capable of dynamic state of charge (SOC) management.
- Predictive curtailment: the controller calculates exactly how much energy is required to fulfil the upcoming evening RCOQ. If local EV charging or embedded network loads are draining the battery too rapidly at 3:00 PM, the controller will automatically throttle or shut off the EV chargers to preserve the battery’s reserve capacity.
- Forced recharging: if a cloudy afternoon prevents the solar array from refilling the battery ahead of the PESROI window, the controller will automatically purchase grid power to force-charge the battery, ensuring it meets the WEM compliance target and avoids AEMO’s financial penalties.
By allowing a third-party aggregator to manage the overarching market signals while the local controller manages the physical limits, a commercial site can stack the guaranteed $360,000+/MW RCM revenue on top of the localised savings from solar optimisation and network peak shaving.
Why participation goes through an aggregator
A facility earning capacity credits must be registered with AEMO by a Market Participant. That does not have to be the site owner, and for a single 1 MW battery it should not be.
Direct participation
The owner registers as a Market Participant and keeps all the revenue. It must also run its own market compliance, 24/7 automated links to AEMO and settlement. For one battery, that overhead is usually not worth it.
Through an aggregator
An aggregator, retailer or virtual power plant operator registers the battery under its own AEMO identity. It carries the market liability, bids the capacity, handles dispatch and settlement, and passes back an agreed share.
The specific percentage that the aggregator takes from Reserve Capacity Mechanism (RCM) payments is not publicly disclosed. It is negotiated privately on a case-by-case basis.
| Aggregator fee (illustrative) | Net payment at A$360,700 | Return over 10 years | Return over 15 years |
|---|---|---|---|
| None | A$360,700 | 7.3% | 11.7% |
| 10% | A$324,630 | 5.1% | 9.8% |
| 20% | A$288,560 | 2.7% | 7.8% |
| 30% | A$252,490 | 0.2% | 5.7% |
Central capital cost A$2.5m, before operating costs and tax. Fee levels are illustrative only; no fee has been quoted.
An aggregator also does not remove the need for a site controller. The battery still has to hold its charge for the evening, share its power with tenants and EV chargers sensibly, and send reliable data to the market. This is the role for the Voltron controller.
The business case for microgrids
A commercial microgrid combines rooftop solar, a battery and a central controller behind a single Western Power connection. In metropolitan Perth the case rests on four drivers.
| Driver | How it pays | Indicative value |
|---|---|---|
| Avoiding a grid upgrade | The battery and solar supply extra capacity on site, so a site can add EV chargers or load without a Western Power upgrade (often 12 to 24 months). | A$100k to A$1M+ of capital avoided, site by site |
| Peak shaving | The battery covers short demand spikes, avoiding network demand charges and the 12-month penalty they can lock in. | A$50k to A$150k+ a year, where the site pays a demand charge |
| Embedded network sales | The owner sells on-site solar to tenants through sub-meters, at a rate a little below the retailer tariff. | Depends on tenant mix and load |
| Capacity payments (RCM) | A battery of at least six hours earns payments for being available at the evening peak (see above). | About A$216k to A$361k per MW a year, before aggregator fees |
What a 1 MW / 6 MWh system costs and returns
Supplied and installed in Perth, excluding any grid upgrade or export connection works. Central estimate about A$2.5m, or about A$415 per kWh.
Capacity payments alone, at A$360,700 per MW a year: about 7% over 10 years, about 12% over 15 years, before operating costs and tax.
Base-case extra from buying and selling energy on the wholesale market (low A$0, high A$34k). It adds less than 2 points to the return.
The components of a microgrid
| Component | What it does |
|---|---|
| Grid connection and gate meter | The single point where the site meets Western Power. Demand charges and any capacity export are measured here. |
| Switchboard and switchgear | Joins every device on a common bus, with protection so the site can isolate faults. |
| Rooftop solar | Low-cost daytime energy for tenants and for charging the battery. |
| Battery and power converter | Stores energy, covers demand spikes and delivers the capacity the RCM pays for. A 1 MW battery needs 6 MWh to meet the six-hour rule. Fire detection and suppression are part of the package. |
| EV chargers | A large load that can arrive in sudden bursts. The controller shares the available power across chargers. |
| Tenant sub-meters | Measure each tenant’s use so on-site energy can be billed. |
| Voltron controller | Decides, every few minutes, when each device charges, discharges or is limited. It protects the evening capacity commitment, shaves peaks and reports to the market. |
| Communications and market link | Secure telemetry to the aggregator and to AEMO. Dispatch instructions arrive about five minutes ahead, so the response must be automatic. |
Using a microgrid to power a micro data centre
To power a micro data centre from a commercial microgrid, the system must isolate the sensitive IT workload from grid volatility while managing the power flow between the solar array, the battery and the local utility. The specification below integrates a continuous edge-compute load (such as a 50 kW Zella DC modular unit) into a 1 MW / 6 MWh commercial microgrid in the Perth South West grid.
Electrical architecture
The strongest design separates site-level energy management from sub-millisecond IT power conditioning by placing the battery upstream of the micro data centre’s internal UPS.
- Grid edge (upstream): a Western Power gate meter is the primary connection point. Directly behind it sit the central microgrid controller and the 1 MW / 6 MWh battery, which reduces grid imports and manages prolonged outages.
- Renewable generation: a commercial rooftop solar array feeds the common AC bus, or the battery directly through DC coupling, for primary daytime generation.
- IT edge (downstream): the micro data centre sits downstream of the main switchboard and uses its own rack-mounted uninterruptible power supply (UPS) for instant ride-through and power conditioning of the critical IT loads.
- Transition mechanism: if the Western Power grid fails, the UPS powers the servers for the few milliseconds it takes the controller to island the site and command the battery to form the local voltage.
Sizing and load apportionment
A battery for critical loads must have enough output (kW) to carry the selected loads and enough energy (kWh) to hold them for the target duration. A microgrid sized for market participation (1 MW / 6 MWh) is well beyond what a standard micro data centre needs.
Typical continuous load of a high-density micro data centre, servers and precision cooling together.
Reserved in the controller to carry a 50 kW load through a 12-hour blackout, out of 6,000 kWh.
Left for peak shaving or RCM dispatch without putting the data centre’s continuity at risk.
Operational control strategy
To protect the IT workload while maximising financial returns, the energy management system cycles through three automated modes.
- Grid-tied optimisation (solar self-consumption and peak shaving). The micro data centre runs 24/7. During the day, the solar array powers the servers directly and excess solar charges the battery. As the sun sets, the controller discharges the battery to cover the load, hiding the continuous draw from Western Power and avoiding daily peak demand charges.
- RCM market dispatch. During the evening Peak Electric Storage Resource Obligation Intervals (PESROI), the controller keeps the battery at its mandatory state of charge. If the aggregator commands a 1 MW market dispatch, the battery discharges into the grid while also powering the local data centre.
- Autonomous islanding (resilience mode). In a regional transformer fault or blackout, the controller opens the main breaker and the microgrid runs on the battery and solar to power the servers, cooling and control systems without interruption.
Component specifications
| Component | Technical requirement | Role |
|---|---|---|
| Micro data centre | 10 kW to 50 kW of IT capacity (for example a Zella DC container) | Houses servers, switching and local precision liquid or air cooling |
| Rack UPS | Double-conversion online UPS, matched to the IT load | Instant power conditioning and protection against sub-second transients |
| Battery (energy storage) | 1 MW inverter and 6 MWh lithium-ion or LiFePO4 | Extended ride-through, peak shaving and site-level load flexibility |
| Microgrid controller | Sub-second programmable logic controller | Automated islanding, generator and solar integration, battery dispatch |
| Solar array | Sized to 150% of the daily continuous IT load | Charges the battery and provides low-cost daytime power to cut retail energy costs |
Using a genset to keep the battery ready for the evening window
To earn RCM payments, the battery must be charged and ready to discharge into the grid during the evening peak window (4:30 pm to 8:00 pm). Solar charging alone can fall short on cloudy days, in winter, or after a daytime dispatch. A biofuel-ready 500 kW genset gives the site a second, dependable way to fill the battery, so it is full before the window opens.
Battery energy that may need refilling before 4:30 pm.
Genset output (625 kVA), prime or standby rated, running on diesel or HVO renewable diesel.
To refill an empty 6 MWh battery from the genset alone, assuming about 95% charging efficiency.
Sizing the recharge
- Full refill: a 1 MW discharge over six hours uses 6 MWh. Refilling that from a 500 kW genset takes about 12.6 hours (6 MWh divided by 500 kW at about 95% efficiency).
- Typical evening: a dispatch at 1 MW from 4:30 pm to 8:00 pm uses 3.5 MWh, which takes about 7.4 hours to refill from the genset alone. Solar reduces this.
- Timing: charging must finish before 4:30 pm, so the controller starts the genset early enough for the energy still needed.
- Backup role: the genset can also carry the micro data centre in a long blackout. That may remove the need to hold a 600 kWh battery reserve and leave the full 6 MWh for the evening window. This needs to be confirmed against the RCM rules.
The charging times are illustrative arithmetic, not figures from the genset specification.
How the controller uses the genset
- Solar first. During the day, solar powers the site and charges the battery. The genset stays off.
- Forecast the shortfall. The controller compares the battery’s state of charge with the target for the evening window. If cloud, winter or an earlier dispatch means it will fall short, it plans a genset run.
- Charge steadily. The genset runs at a steady load to fill the battery and finishes before 4:30 pm.
- Stop and discharge. From 4:30 pm to 8:00 pm the battery discharges 1 MW to the grid on the aggregator’s dispatch instruction, while still covering the site load. The genset is not needed.
Genset specification
| Item | Specification |
|---|---|
| Power output | 500 kW / 625 kVA, prime or standby |
| Fuel | Standard diesel, and fully compatible with HVO (hydrotreated vegetable oil) as a drop-in renewable fuel that cuts lifecycle carbon emissions |
| Emissions | US EPA Tier 4 Final or EU Stage V, the strictest standards, suited to urban and regulated commercial sites |
| Engine | Heavy-duty industrial diesel, for example 18.1 litre units such as the Caterpillar C18 or the Perkins engine used in Generac models |
| Noise | 60 to 70 dB(A) at 7 metres in a super-silent (Level III) sound-attenuated enclosure. An open unit exceeds 100 dB(A) and is not acceptable near offices and retail |
| Enclosure and silencer | 1.5 mm to 2 mm steel or aluminium with mass-loaded vinyl or mineral wool insulation, and a hospital-grade silencer giving a further 25 to 35 dB(A) reduction |
| Vibration | Spring isolators or rubber-in-shear mounts on the skid to stop vibration passing into the building |
| Footprint and weight | About 5.2 m long, 1.8 m wide and 4.0 m high enclosed. 7,800 kg dry and up to 8,700 kg with fuel |
| Controls and integration | Digital control panel with real-time monitoring and cloud diagnostics, automatic transfer switch compatibility, and parallel-ready for a larger microgrid |
Noise, air emissions and fuel storage approvals for a metropolitan site are not covered by the specification and would need to be confirmed with the local authority.
The business case: a genset instead of a 500 kW Western Power connection
The site needs 500 kW of dependable capacity for its battery recharging, EV chargers or a micro data centre. There are two ways to get it: apply to Western Power for a permanent 500 kW network upgrade, or install a biofuel-ready genset behind the meter as part of the microgrid.
Estimated cost of a premium 500 kW HVO-ready genset built to the Tier 4 Final and super-silent specification.
Estimated Western Power construction cost for a dedicated transformer, high-voltage cable and network upgrade, plus A$3,388 to A$6,776 in design fees.
Western Power’s stated timeline for 75% of medium and large connections, against 4 to 12 weeks for the genset.
| Item | 500 kW genset | 500 kW Western Power connection (import) |
|---|---|---|
| Capital cost | A$180,000 to A$280,000 for a premium brand (such as Caterpillar, Kohler/SDMO or Denyo) built to this specification. A standard diesel set costs about A$40,000 to A$60,000 | A$150,000 to over A$400,000, depending on distance to the nearest capable high-voltage feeder, plus A$3,388 to A$6,776 in non-refundable design fees |
| Time to power | 4 to 12 weeks, delivered and installed, depending on stock | 9 to 19 months for 75% of projects: 5 to 9 months of design and 4 to 10 months of construction |
| Land and footprint | An enclosed unit of about 5.2 m by 1.8 m by 4.0 m | Land surrendered to Western Power for a high-voltage pad-mount transformer and switchgear |
| Ongoing charges | No network demand tariff on the genset’s output, but fuel, maintenance and AdBlue costs | An import connection brings ongoing network demand (capacity) charges, with the rolling 12-month ratchet. An export-only connection is charged differently and avoids the demand tariff |
| What drives the price | Tier 4 Final exhaust after-treatment (particulate filter and AdBlue catalyst) and a custom Level III acoustic enclosure | Network construction and headworks |
Where the genset wins
- Speed: the site can switch on its data centre, retail loads or EV chargers in weeks, not 9 to 19 months. A year or more of lost trading revenue is avoided.
- Capital cost: the two ranges overlap, so the genset is at cost parity or better, and the grid upgrade becomes the more expensive option when the site is far from a capable feeder.
- Ongoing charges: a new import connection locks the site into network demand charges for the capacity it draws. Using the genset, or the battery microgrid, behind the meter avoids those charges and the 12-month ratchet. As an illustration, at the A$146 per kVA per year rate quoted in the project research (not yet verified), 500 kVA of capacity would cost about A$73,000 a year.
Points to weigh
- Running costs: the comparison is mainly capital and time. It does not include the genset’s fuel (diesel or HVO), AdBlue, servicing and replacement over its life.
- Not a like-for-like supply: a grid connection is permanent, firm capacity. In this design the genset tops up the battery, which carries the evening load and the RCM dispatch.
- Export connection still needed: the battery sends 1 MW into the grid for RCM dispatch, and an export connection must be able to carry that peak just as a load connection must. The genset avoids an import connection, not the export one. Unless the site already has spare export capacity, it needs a Western Power enquiry, and an export upgrade could bring similar cost and delay (A$150,000 or more, and 9 to 19 months).
- Cost range overlap: if the site is close to a capable high-voltage feeder, the connection could cost less than the genset.
- Estimates only: the cost and timeline figures are indicative and unquoted. Supplier quotes and a Western Power connection enquiry would replace them.