Truck Charging – Options for Microgrids, RCM Revenue Streams and Project Jupiter
This briefing explores options for powering truck charging with a microgrid, and the revenue streams available to it from the WA RCM scheme and Project Jupiter.
See how a 7 MWh* battery depletes over a day with solar and charging load
Summary
1. Truck charging
ARENA’s Driving the Nation Focus Area 2 funds heavy battery-electric vehicle charging, including megawatt charging and freight hubs serving multiple customers. The expected grant is at least $1 million toward initial capex and the operational funding gap. Single-fleet depots are out of scope.
2. RCM revenue stream
A 1 MW / 7 MWh* battery can earn capacity payments from the WA Reserve Capacity Mechanism, with participation through an aggregator.
3. Project Jupiter
Project Jupiter is a three-year program of about A$108 million, led by Western Power with Synergy and AEMO and funded in part by ARENA. It is building the rules and market platform that let aggregated batteries earn from network support and capacity services. A truck hub’s battery could join through its aggregator. Eligibility for a site of this size and payment rates are still to be confirmed.
4. Microgrids
A battery, solar and EV chargers behind one grid connection can earn from several sources: avoided grid upgrades, peak shaving, tenant energy sales and capacity payments.
5. Voltron controller
The proprietary control platform developed in-house drives system reliability and maximises project yield. The software gives Voltron complete architectural control, allowing us to tailor dispatch logic, peak-shaving thresholds, and automation protocols directly to each client’s specific operational requirements.
*7 MWh is the usable energy in the battery. A battery with 7 MWh usable needs to be sized at at least 8.5 MWh.
ARENA Focus Area 2: deployment of heavy BEV charging solutions
ARENA’s Driving the Nation program, Focus Area 2, seeks to accelerate the uptake of heavy battery-electric vehicles (BEVs) by supporting the deployment of charging solutions.
Deploy charging infrastructure
Charging solutions that service heavy BEVs, including mixed-use scenarios involving trucks, buses and other vehicles.
Optimise grid integration
Charging solutions that address the high-capacity requirements of heavy BEVs and grid constraints.
The expected size of a grant. The Program Guidelines add that applicants are typically expected to at least match the grant sought.
Projects ARENA wants to support
- Freight charging hubs for multiple customers at strategic locations.
- Freight corridors and long-haul infrastructure to support en-route and highway charging, including green corridors.
- High-capacity charging, including megawatt charging.
- Mixed-use scenarios.
- Inter-modal freight hubs, including ports.
- Charging as a service for owner-operators and smaller fleet operators.
Who ARENA expects to apply
A range of applicants with the capability and resources to develop and deploy charging infrastructure, which may be a consortium or partnership of charge point operators, renewable energy developers, distributed network service providers (DNSPs), infrastructure investors (debt and equity), and customers such as distribution centres, warehouses, ports, corporate customers and real estate developers.
What the grant pays for
- A portion of the charging infrastructure, electrical upgrades and installation costs, to part-fund the initial capex.
- A portion of the operational funding gap.
What a project must show, and what is out
- A feasibility study or analysis supporting the selection of the proposed sites.
- Not in scope: depot or back-to-base charging infrastructure catering to a single fleet.
How a hybrid truck-charging forecourt lines up
- Multiple customers: a service station open to owner-operators and several fleets is a shared hub, not a single-fleet depot, so it stays in scope.
- Megawatt charging within a grid constraint: two megawatt (MCS) bays behind a 1 MW connection, with a battery buffer, speaks directly to the grid-integration requirement.
- Mixed use: the bays sit alongside petrol and diesel dispensers on the same site.
- Feasibility study: one that supports the choice of site has to be completed before an application.
- Scale: whether a two-bay site can carry a grant of at least $1 million is an open question.
Source: ARENA, Driving the Nation Program Focus Areas, 15 October 2025. The forecourt comparison is Chargestar’s own reading.
What is the Reserve Capacity Mechanism and how does it work?
Western Australia’s South West grid is a stand-alone system, so it must always hold enough generating and storage capacity to meet the highest demand, with a safety margin. The Reserve Capacity Mechanism (RCM) pays owners of capacity for being available when needed, whether or not they are used.
- Capacity is certified. A facility is assigned capacity credits for the power it can reliably deliver. The operator is paid on the rated output of the battery over one hour, and the battery must have the capacity to discharge for the full duration requirement, which is seven hours from the 2028-29 capacity year (six hours for 2027-28). A 7 MWh* battery discharging at 1 MW over seven hours is awarded one capacity credit. For batteries coming on line in 2027, under the six-hour requirement, a credit is worth A$360,700 per year.
- A price is set. The Economic Regulation Authority sets the Reserve Capacity Price, in dollars per MW per year, for each capacity year. It now uses a battery as the reference technology.
- The owner is paid for availability. Each year the facility is paid the price multiplied by its capacity credits, in return for being ready.
- It must be ready when called. The obligation falls on the evening peak. Operators are told the intervals in advance, then receive the dispatch instruction about five minutes before power is needed. The battery must be charged and responding automatically. Missing the obligation attracts financial penalties.
What the payments look like
| Capacity year | Reserve Capacity Price (per MW per year) | Payment for 1 MW |
|---|---|---|
| 2025-26 | A$251,420 | A$251,420 |
| 2026-27 | A$216,092 | A$216,092 |
| 2027-28 | A$360,700 | A$360,700 |
A 7 MWh* battery discharging at 1 MW earns one credit, as credits are awarded on a one credit per MW of capacity basis. The prices in the table are for earlier capacity years, when the requirement was six hours or less, and the price changes with each cycle, so revenue cannot be assumed to stay at the 2027-28 level. Payments are before the aggregator’s share, tax and operating costs.
The seven-hour duration requirement
AEMO’s 2026 Electricity Statement of Opportunities sets the battery duration requirement at seven hours for the 2028-29 capacity year, up from six hours for 2027-28. To earn a full capacity credit, a new 1 MW battery must be able to discharge 1 MW for seven hours, which takes 7 MWh*.
- Shorter batteries are de-rated. A 2-hour or 4-hour battery is not shut out, but it earns a fraction of the credits a 7-hour battery of the same power would.
- Less certain revenue. Capacity payments are the steadiest revenue stream a battery has, so losing part of them makes a project harder to finance and pushes it towards less predictable energy-market income.
- More battery to buy. Meeting the full requirement means more cells for the same power, which raises the up-front cost. This site is sized at 7 MWh* for that reason.
*7 MWh is the usable energy in the battery. A battery with 7 MWh usable needs to be sized at at least 8.5 MWh.
Source: AEMO, 2026 Wholesale Electricity Market Electricity Statement of Opportunities. The de-rating and finance points are Chargestar’s reading and the credit calculation for a battery online from 2028-29 has not been checked against the WEM Rules.
Can a battery operator in a microgrid take advantage of the RCM while still using the battery for other purposes?
To take advantage of the Reserve Capacity Mechanism (RCM) while dual-purposing the battery for local microgrid needs, an operator must divide the battery’s daily schedule into two operational states. This is achieved by using an intelligent Energy Management System (EMS) to manage the strict compliance boundaries set by the Wholesale Electricity Market (WEM).
The strategy relies on separating the legally binding RCM obligations from free commercial use.
1. Navigating the PESROI window (grid priority)
Under WEM rules, a battery receiving capacity payments does not belong to AEMO 24/7. It is only strictly obligated to the grid during the Peak Electric Storage Resource Obligation Intervals (PESROI), the critical evening peak window defined by AEMO.
- The RCOQ mandate: during the PESROI, the battery has a Reserve Capacity Obligation Quantity (RCOQ). It must hold a sufficient state of charge (SOC) to discharge its contracted megawatt capacity into the broader South West Interconnected System (SWIS) if AEMO issues a 5-minute dispatch instruction.
- Penalty avoidance: if the battery cannot meet this dispatch instruction because it was depleted by local microgrid loads, AEMO will levy severe financial penalties known as Capacity Refunds, which can quickly wipe out the site’s capacity revenue. During this window, grid compliance overrides all local site optimisation.
2. Freedom outside the window (microgrid priority)
Outside of the evening PESROI window, the RCOQ drops to zero. The battery is legally freed from its AEMO capacity obligations and can be cycled for local financial benefit:
- Morning and midday solar soaking: the battery absorbs excess generation from the microgrid’s commercial rooftop solar array that would otherwise be wasted or exported for minimal return.
- Daytime peak shaving: if the site’s commercial operations or EV chargers suddenly spike demand at 1:00 PM, the battery discharges locally to shave the peak, shielding the site from Western Power’s 12-month demand ratchet penalties.
- Wholesale arbitrage: the site’s aggregator can bid the battery’s spare capacity into the 5-minute energy or frequency (FCESS) markets to capture daytime price spikes, provided there is enough time to recharge before the evening peak.
3. The role of the microgrid controller (dynamic SOC management)
To run this dual-use model safely without human intervention, the site must install an advanced microgrid controller capable of dynamic state of charge (SOC) management.
- Predictive curtailment: the controller calculates exactly how much energy is required to fulfil the upcoming evening RCOQ. If local EV charging or embedded network loads are draining the battery too rapidly at 3:00 PM, the controller will automatically throttle or shut off the EV chargers to preserve the battery’s reserve capacity.
- Forced recharging: if a cloudy afternoon prevents the solar array from refilling the battery ahead of the PESROI window, the controller will automatically purchase grid power to force-charge the battery, ensuring it meets the WEM compliance target and avoids AEMO’s financial penalties.
By allowing a third-party aggregator to manage the overarching market signals while the local controller manages the physical limits, a commercial site can stack the guaranteed $360,000+/MW RCM revenue on top of the localised savings from solar optimisation and network peak shaving.
Why participation goes through an aggregator
A facility earning capacity credits must be registered with AEMO by a Market Participant. That does not have to be the site owner, and for a single 1 MW battery it should not be.
Direct participation
The owner registers as a Market Participant and keeps all the revenue. It must also run its own market compliance, 24/7 automated links to AEMO and settlement. For one battery, that overhead is usually not worth it.
Through an aggregator
An aggregator, retailer or virtual power plant operator registers the battery under its own AEMO identity. It carries the market liability, bids the capacity, handles dispatch and settlement, and passes back an agreed share.
The specific percentage that the aggregator takes from Reserve Capacity Mechanism (RCM) payments is not publicly disclosed. It is negotiated privately on a case-by-case basis.
| Aggregator fee (illustrative) | Net payment at A$360,700 | Return over 10 years | Return over 15 years |
|---|---|---|---|
| None | A$360,700 | 7.3% | 11.7% |
| 10% | A$324,630 | 5.1% | 9.8% |
| 20% | A$288,560 | 2.7% | 7.8% |
| 30% | A$252,490 | 0.2% | 5.7% |
Central capital cost A$2.5m, before operating costs and tax. Fee levels are illustrative only; no fee has been quoted.
An aggregator also does not remove the need for a site controller. The battery still has to hold its charge for the evening, share its power between the charging bays and the forecourt sensibly, and send reliable data to the market. This is the role for the Voltron controller.
The business case for microgrids
A commercial microgrid combines rooftop solar, a battery and a central controller behind a single Western Power connection. In metropolitan Perth the case rests on four drivers.
| Driver | How it pays | Indicative value |
|---|---|---|
| Avoiding a grid upgrade | The battery and solar supply extra capacity on site, so a site can add EV chargers or load without a Western Power upgrade (often 12 to 24 months). | A$100k to A$1M+ of capital avoided, site by site |
| Peak shaving | The battery covers short demand spikes, avoiding network demand charges and the 12-month penalty they can lock in. | A$50k to A$150k+ a year, where the site pays a demand charge |
| Embedded network sales | The owner sells on-site solar to tenants through sub-meters, at a rate a little below the retailer tariff. | Depends on tenant mix and load |
| Capacity payments (RCM) | A battery that can discharge for the full required duration (seven hours from 2028-29) earns payments for being available at the evening peak (see above). | About A$216k to A$361k per MW a year, before aggregator fees |
What a 1 MW / 7 MWh* system costs and returns
Supplied and installed in Perth, excluding any grid upgrade or export connection works. Central estimate about A$2.5m, or about A$357 per kWh at 7 MWh*. This assumes a 7 MWh* system costs about the same as the earlier 6 MWh estimate as battery prices fall. It is not a quote.
Capacity payments alone, at A$360,700 per MW a year: about 7% over 10 years, about 12% over 15 years, at the 2027-28 price and before operating costs and tax.
Base-case extra from buying and selling energy on the wholesale market (low A$0, high A$34k). It adds less than 2 points to the return.
The components of a truck-charging microgrid
| Component | What it does |
|---|---|
| Grid connection and gate meter | The single 1 MW point where the site meets Western Power. Demand charges and any capacity export are measured here. |
| Switchboard and switchgear | Joins every device on a common bus, with protection so the site can isolate faults. |
| Solar canopy and roof | Low-cost daytime energy for the charging bays, the forecourt and the battery. |
| Battery and power converter | Stores energy, covers charging above the 1 MW import limit outside the evening window, and delivers the capacity the RCM pays for. A 1 MW RCM credit needs 7 MWh* to meet the seven-hour requirement. Fire detection and suppression are part of the package, and on a fuel site fire engineering is likely to take longest. |
| MCS charging bays | Two megawatt bays, a large load that arrives in bursts. The controller shares the available power between the bays. |
| HVO gensets | Refill the battery before 4:00 pm and supply charging while the battery is held for the evening window. |
| Forecourt loads and billing meters | Fuel dispensers, shop and lighting on a protected supply. Billing meters per customer, so each fleet or owner-operator pays for the energy it takes. |
| Voltron controller | Decides, every few minutes, when each device charges, discharges or is limited. It protects the evening capacity commitment, shaves peaks and reports to the market. |
| Communications and market link | Secure telemetry to the aggregator and to AEMO. Dispatch instructions arrive about five minutes ahead, so the response must be automatic. |
Using a microgrid to power electric truck charging
This specification adds two megawatt charging (MCS) bays to a service station that keeps its petrol and diesel dispensers. The site has a 1 MW Western Power connection, a 7 MWh* battery, solar and HVO-ready gensets. The battery is held for the RCM and grid support between 4:00 pm and 11:00 pm, so the design must serve trucks without relying on it in that window. All figures below are indicative sizing assumptions, not quotes or a finished design.
Electrical architecture
A forecourt is a classified hazardous area around its dispensers, fill points and tank vents. The charging cabinets, battery, inverter and gensets must sit outside those zones, so the hazardous area drawing comes first.
- Grid edge: a Western Power gate meter marks the 1 MW connection. Directly behind it sit the microgrid controller and the battery. The controller holds the site’s import at or below 1 MW.
- Common AC bus: the switchboard joins the battery inverter, solar inverters, gensets, the charging power cabinets and the forecourt loads. Whether the battery is AC-coupled or DC-coupled to the charging equipment is a design choice. DC coupling saves a conversion step but ties RCM export to the chargers; AC coupling keeps them independent.
- Charging bays: each MCS bay is fed by a power cabinet that converts AC to DC at up to 1,250 V and 3,000 A, delivered through a liquid-cooled cable and connector. This design assumes 1.0 MW per bay; commercial chargers today run from 1.0 to 1.44 MW.
- Generation: solar on the canopy and roof feeds the AC bus. HVO-ready gensets connect through their own breaker and synchronise with the grid or the battery inverter.
- Protected forecourt supply: fuel dispensers, forecourt controls and emergency lighting sit on a protected section of the bus, integrated with the site’s existing emergency power-off. The truck bays are shed first.
- Transition mechanism: if the Western Power grid fails, the controller opens the main breaker and commands the battery to form the local grid, starting the gensets if needed. Fuel dispensing continues; truck charging continues only as far as supply allows.
Sizing and load apportionment
Two 1 MW bays can ask for twice the connection. The battery inverter covers the gap, and the battery’s energy is kept for the evening window.
Peak charging demand, with both MCS bays at 1.0 MW.
Import limit of the Western Power connection.
Gap to cover from the battery, solar and gensets when both bays run flat out, with 100 kW of forecourt load assumed. The forecourt load needs to be metered.
Battery inverter and energy. The inverter is above 1 MW so it can cover the gap. The RCM credit stays at 1 MW, which needs 7 MWh* over seven hours. Whether the larger inverter affects certification needs checking against the WEM rules.
Energy in one truck session, taking a 600 to 900 kWh pack from 20% to 80%. That is about 22 to 32 minutes at 1 MW.
The battery dispatches in the window: 1 MW for the 7 hours from 4:00 pm to 11:00 pm, which uses all of it.
Grid power needed from 11:00 pm to 6:00 am to refill 7 MWh* in seven hours at 95% efficiency. The 1 MW connection gives 6.65 MWh, which is 95% full and 350 kWh short.
Nameplate size needed for 7 MWh* of usable energy. The 7 MWh* figures on this page are usable energy.
| Period | What the battery does | How trucks are charged |
|---|---|---|
| 11:00 pm to 4:00 pm the next day | Recharges overnight from the grid at up to the 1 MW import limit. It is then free for local use: it soaks up midday solar, covers the gap above the 1 MW import limit, and recharges from solar, the grid or the gensets. It must be full by 4:00 pm. | Both bays at full rate: up to 1 MW from the grid, with the battery covering the rest. |
| 4:00 pm to 11:00 pm | Held for the RCM and grid support, with the full 7 MWh* available. | From the grid (up to 1 MW), solar and the gensets. If a dispatch instruction arrives, grid support has priority and the controller reduces charging to what the gensets and solar can supply. |
*7 MWh is the usable energy in the battery. A battery with 7 MWh usable needs to be sized at at least 8.5 MWh. The cost figures on this page have not been re-priced for the larger nameplate.
How a dispatch is measured, at the gate meter or at the battery, needs to be confirmed with the aggregator, because it decides how much charging can continue during a dispatch.
Operational control strategy
To keep trucks moving while protecting the evening commitment, the energy management system cycles through four automated modes.
- Grid-tied optimisation (outside the window). Solar charges the trucks and the battery first. The battery covers the gap above the 1 MW limit, so both bays can run at full rate without a larger connection and without a new demand peak. The battery recharges from solar and cheap grid energy and must be full by 4:00 pm. If it will fall short, the controller starts the gensets early.
- RCM and grid support (4:00 pm to 11:00 pm). The controller holds the battery’s state of charge. Trucks are served from the grid, solar and gensets. On a dispatch instruction the battery discharges up to 1 MW to the grid for the seven hours, while charging is reduced as above.
- Overnight recharge (11:00 pm to 6:00 am). The battery recharges from the grid at up to the 1 MW import limit, on the cheap overnight rate. Refilling 7 MWh* in seven hours takes about 1.05 MW at 95% efficiency, so at 1 MW it reaches about 6.65 MWh by 6:00 am, 350 kWh short. The gensets and solar make up the difference before 4:00 pm.
- Autonomous islanding (resilience mode). In a regional transformer fault or blackout the controller opens the main breaker. The battery and gensets keep the fuel dispensers and forecourt controls running, and truck charging continues only as far as supply allows.
Component specifications
| Component | Technical requirement | Role |
|---|---|---|
| MCS charging bays (2) | Up to 1.0 MW each, up to 1,250 V DC and 3,000 A, liquid-cooled cable, one power cabinet per bay | Charges heavy trucks within a 30 to 45 minute driver break |
| Fuel dispensers | Existing petrol and diesel dispensers, unchanged, on the protected supply | Keep serving vehicles and set the hazardous zones the new equipment must avoid |
| Battery (energy storage) | 1.5 MW inverter and 7 MWh* usable (at least 8.5 MWh nameplate) lithium-ion or LiFePO4 | Covers charging above the 1 MW limit outside the window; held for RCM and grid support from 4:00 pm to 11:00 pm |
| HVO gensets | 500 kW / 625 kVA in total, one set or several, diesel or HVO | Refill the battery before 4:00 pm, supply charging in the window and back up the forecourt |
| Solar array | Canopy and roof, sized to the area available (size to be confirmed) | Charges trucks and the battery and cuts daytime energy costs |
| Microgrid controller | Sub-second controller with OCPP and Modbus links to the chargers | Holds import to 1 MW, shares power between the bays, keeps the battery reserve for the window, starts the gensets and islands the site |
From the network operator to the truck hub
A dispatch request passes through three layers before it moves any equipment. Each layer translates the one above into something it can act on, and the site controller is the only layer that writes to the equipment.
Western Power
Estimates power flows across the high-voltage and low-voltage network and works out what each connection point may import or export. It talks to aggregators, not to individual batteries.
Shell Energy
Operates the truck refuelling station and acts as its VPP aggregator. Cloud portfolio dispatch decides which sites act, using state of charge, battery wear cost and local load, and converts the fleet target into one setpoint per site.
Voltron microgrid controller
Sits inside the site fence. Checks each setpoint against transformer, breaker, ramp and export limits and against its own reserve rules, then splits the result across the equipment below. Every decision is logged with the constraints it checked.
Solar PV
Modbus / SunSpecCurtails output and holds the export limit.
Battery
Modbus TCP / CANCharge and discharge power through the inverter. Holds a reserve for charging sessions.
Site load
Meter + ModbusReads the site meter and sheds lower-priority loads.
HVO genset
Modbus / genset controllerStarts and synchronises to refill the battery, or is inhibited when it is not needed.
EV charging
Modbus TCP + OCPPSets hard kW limits per charger group. Each charger keeps its own OCPP session for billing. OCPP proxy is the fallback.
Using a genset to keep the battery ready for the evening window
To earn RCM payments, the battery must be charged and ready to discharge into the grid during the evening peak window (4:00 pm to 11:00 pm). Solar charging alone can fall short on cloudy days, in winter, or after a daytime dispatch. A biofuel-ready 500 kW genset gives the site a second, dependable way to fill the battery, so it is full before the window opens.
Battery energy that may need refilling before 4:00 pm.
Total genset output (625 kVA), prime or standby rated, running on diesel or HVO renewable diesel.
To refill an empty 7 MWh* battery from the genset alone, assuming about 95% charging efficiency.
Sizing the recharge
- Full refill: a 1 MW discharge over seven hours uses 7 MWh*. Refilling that from a 500 kW genset takes about 14.7 hours (7 MWh* divided by 500 kW at about 95% efficiency).
- Typical evening: a dispatch at 1 MW from 4:00 pm to 11:00 pm uses all 7 MWh*, which takes about 14.7 hours to refill from the genset alone. Overnight grid charging at the 1 MW import limit refills most of it by 6:00 am, and the genset and solar cover the remaining shortfall before 4:00 pm.
- Timing: charging must finish before 4:00 pm, so the controller starts the genset early enough for the energy still needed.
- Charging and backup role: in the evening window the gensets can supply truck charging so the battery stays whole for dispatch, and in a long blackout they can carry the forecourt’s protected loads. This needs to be confirmed against the RCM rules.
The charging times are illustrative arithmetic, not figures from the genset specification.
How the controller uses the genset
- Solar first. During the day, solar powers the charging bays and forecourt and charges the battery. The genset stays off.
- Forecast the shortfall. The controller compares the battery’s state of charge with the target for the evening window. If cloud, winter or an earlier dispatch means it will fall short, it plans a genset run.
- Charge steadily. The genset runs at a steady load to fill the battery and finishes before 4:00 pm.
- Stop and discharge. From 4:00 pm to 11:00 pm the battery is held for dispatch and discharges 1 MW to the grid on the aggregator’s dispatch instruction. The genset can supply truck charging during this time.
Genset specification
| Item | Specification |
|---|---|
| Power output | 500 kW / 625 kVA in total, across one set or several, prime or standby |
| Fuel | Standard diesel, and fully compatible with HVO (hydrotreated vegetable oil) as a drop-in renewable fuel that cuts lifecycle carbon emissions |
| Emissions | US EPA Tier 4 Final or EU Stage V, the strictest standards, suited to urban and regulated commercial sites |
| Engine | Heavy-duty industrial diesel, for example 18.1 litre units such as the Caterpillar C18 or the Perkins engine used in Generac models |
| Noise | 60 to 70 dB(A) at 7 metres in a super-silent (Level III) sound-attenuated enclosure. An open unit exceeds 100 dB(A) and is not acceptable near offices and retail |
| Enclosure and silencer | 1.5 mm to 2 mm steel or aluminium with mass-loaded vinyl or mineral wool insulation, and a hospital-grade silencer giving a further 25 to 35 dB(A) reduction |
| Vibration | Spring isolators or rubber-in-shear mounts on the skid to stop vibration passing into the building |
| Footprint and weight | About 5.2 m long, 1.8 m wide and 4.0 m high enclosed. 7,800 kg dry and up to 8,700 kg with fuel |
| Controls and integration | Digital control panel with real-time monitoring and cloud diagnostics, automatic transfer switch compatibility, and parallel-ready for a larger microgrid |
Noise, air emissions and fuel storage approvals for a metropolitan site are not covered by the specification and would need to be confirmed with the local authority. Like the battery, the gensets must sit outside the forecourt’s classified hazardous zones.
The business case: a genset instead of a 500 kW Western Power connection
The site needs about 500 kW of dependable capacity beyond its 1 MW connection, for battery recharging and truck charging. There are two ways to get it: apply to Western Power for a permanent 500 kW network upgrade, or install a biofuel-ready genset behind the meter as part of the microgrid.
Estimated cost of a premium 500 kW HVO-ready genset built to the Tier 4 Final and super-silent specification.
Estimated Western Power construction cost for a dedicated transformer, high-voltage cable and network upgrade, plus A$3,388 to A$6,776 in design fees.
Western Power’s stated timeline for 75% of medium and large connections, against 4 to 12 weeks for the genset.
| Item | 500 kW genset | 500 kW Western Power connection upgrade (import) |
|---|---|---|
| Capital cost | A$180,000 to A$280,000 for a premium brand (such as Caterpillar, Kohler/SDMO or Denyo) built to this specification. A standard diesel set costs about A$40,000 to A$60,000 | A$150,000 to over A$400,000, depending on distance to the nearest capable high-voltage feeder, plus A$3,388 to A$6,776 in non-refundable design fees |
| Time to power | 4 to 12 weeks, delivered and installed, depending on stock | 9 to 19 months for 75% of projects: 5 to 9 months of design and 4 to 10 months of construction |
| Land and footprint | An enclosed unit of about 5.2 m by 1.8 m by 4.0 m | Land surrendered to Western Power for a high-voltage pad-mount transformer and switchgear |
| Ongoing charges | No network demand tariff on the genset’s output, but fuel, maintenance and AdBlue costs | An import connection brings ongoing network demand (capacity) charges, with the rolling 12-month ratchet. An export-only connection is charged differently and avoids the demand tariff |
| What drives the price | Tier 4 Final exhaust after-treatment (particulate filter and AdBlue catalyst) and a custom Level III acoustic enclosure | Network construction and headworks |
Where the genset wins
- Speed: the site can add truck charging capacity in weeks, not 9 to 19 months. A year or more of lost trading revenue is avoided.
- Capital cost: the two ranges overlap, so the genset is at cost parity or better, and the grid upgrade becomes the more expensive option when the site is far from a capable feeder.
- Ongoing charges: a new import connection locks the site into network demand charges for the capacity it draws. Using the genset, or the battery microgrid, behind the meter avoids those charges and the 12-month ratchet. As an illustration, at the A$146 per kVA per year rate quoted in the project research (not yet verified), 500 kVA of capacity would cost about A$73,000 a year.
Points to weigh
- Running costs: the comparison is mainly capital and time. It does not include the genset’s fuel (diesel or HVO), AdBlue, servicing and replacement over its life.
- Not a like-for-like supply: a grid connection is permanent, firm capacity. In this design the genset tops up the battery, which carries the evening load and the RCM dispatch.
- Export connection still needed: the battery sends 1 MW into the grid for RCM dispatch, and an export connection must be able to carry that peak just as a load connection must. The genset avoids an import connection, not the export one. Unless the site already has spare export capacity, it needs a Western Power enquiry, and an export upgrade could bring similar cost and delay (A$150,000 or more, and 9 to 19 months).
- Cost range overlap: if the site is close to a capable high-voltage feeder, the connection could cost less than the genset.
- Estimates only: the cost and timeline figures are indicative and unquoted. Supplier quotes and a Western Power connection enquiry would replace them.